The Lee & Man Project in Vietnam Undertaken by the Company successfully Brought into Operation

Browsing volume:1139 Hits: Source: Date:2017-03-10

 

 

On March 8, the 400,000 t/a packaging paper production line project of Vietnam Lee & Man Paper Manufacturing Limited generally contracted by the Company started to output paper, which marked the successful commissioning of this project, and brought the 3-year project service of Haisum to a satisfactory end.

 

 

For the Lee & Man project in Vietnam: The contract was successfully concluded in February 2014; the civil works were commenced on December 23, 2014; the first batch of exported equipment departed from the port on August 27, 2015; the equipment was delivered for installation in November 2015; the installation was finished in August 2016; paper was output successfully on March 8, 2017. The Company, as the general contractor of the project, was in charge of the design, civil construction, domestic equipment purchase, and complete set export etc.

 

Founded in 1994, Lee & Man Paper Manufacturing Limited (“Lee & Man Paper”) has evolved into one of the global leading carton base paper and pulp manufacturers. Over more than 20 past years since its engagement in the design of Lee & Man Dongguan (Lee & Mans first factory), Haisum has participated in the construction of all its factories in Jiangsu, Guangdong, Chongqing, Jiangxi and Vietnam in terms of site selection, consultation through design and engineering management to EPC, having accompanied and witnessed the development history of Lee & Man Paper.

 

As the third finished project of the Company in Vietnam following Anhua pulp mill and VKPC paper mill, Lee & Man project in Vietnam marked that Haisum Co., Ltd. took a successful step forward in overseas projects.

 

 

 